01 / Pilot · March–August 2026
PermitLite
A six-step mobile workflow for selected small construction permits, with document checklists, status tracking, and a staff review queue alongside the municipality’s existing records system.
Municipality in the western United States · ~12,000 residents · names withheld
Read the PermitLite case- Follow-up for missing documents: 14 of 34 applications (41%) before, 8 of 39 (21%) after.
- Median time to a complete file: 3.6 to 2.4 business days.